Objective: Works to be carried out during a 1-week window (Summer Holiday shutdown).
DPC contracts removed over 300m2 of defective main works yard which was 300mm in depth. This area was then re-concreted and ready for use in 4 days in total. The main challenge in this work was to achieve completion within the 5-day window during the August shut-down.